Statue Of Equality – 10th Weekly Report Of the Project from China

Report dated 9th,Sep,2016

1:1 model construction of Bhagavad Ramanujacharya is 95% complete. One of our sculptors will soon visit Nanjing workshop for inspecting and conducting final checks. Casting of Lotus and Elephants is complete. Casting of Body parts is in progress, 1-4 levels of work is complete and the levels 5-17 is in progress.

10th Week – Workshop photos

2017-08-27T09:55:44+00:00 September 10th, 2016|Comments Off on Statue Of Equality – 10th Weekly Report Of the Project from China